Construction Notice - Hostettler Road Closure
March 25, 2026
Hostettler Road Closure – Phase 2
Phase 2 of the Hostettler Road project is scheduled to begin a full road closure on Monday, March 30 through June 1.
What to Expect
In preparation for the full closure, intermittent lane closures with flagging may occur during the week prior to March 30.
During the Closure
- Hostettler Road will be closed to through traffic
- Emergency access will be maintained at all times
Work Activities
Construction activities will include:
- Groundwater dewatering using pumps and catchment tanks
- Waterline relocation
- Drainage culvert installation
Dewatering operations are expected to occur during the first several weeks before excavation work begins.
Additional Information
The duration of the road closure is weather and groundwater level dependent and may change as needed.
Motorists are encouraged to plan ahead, use alternate routes, and follow all posted signage and traffic control measures.