Blythe Resurfacing - Project Update

February 24, 2026

We’ve completed the replacement of 5 miles of existing asphalt pavement on 6th Avenue, from west of De Frain Boulevard to Intake Boulevard/SH‑95, and 1.6 miles of asphalt pavement on 10th Avenue between Arrowhead Boulevard and De Frain Boulevard in the community of West Blythe.

 

The contractor will continue with shoulder backfilling, utility adjustments, and additional improvements. The project is anticipated to be completed by the end of February 2026 (weather permitting).

 

Please use caution while traveling through the work zone. Thank you for your patience and understanding as we work to improve roadway safety and mobility.